Planning Questions & FAQs
Answers on planning intelligence, masterplanning, project leadership, specialist coordination, applications and the work needed to implement consent.
Planning questions
What should we establish before acquiring or investing in a site?
Start with the decision the investment needs to support. Review the planning history, current uses, permissions, policy context and constraints alongside the proposed development objective. Identify which assumptions need further evidence before capital is committed.
Planning questions
The site already has permission. What still needs checking?
Read the decision notice with the approved plans, condition approvals, obligations and implementation records. Establish which consent is being relied on and whether it supports the scheme and programme now proposed.
Planning questions
Could permitted development provide the route forward?
In England, some development benefits from permission granted nationally. The proposed works or use must meet the relevant limits and conditions; restrictions and prior-approval requirements may apply. A change of use and associated building works may need separate consideration.
Planning questions
Who leads the masterplanning and runs the project?
STAGE is the masterplanner. We run the whole project and coordinate the full professional team, bringing planning strategy, architecture, masterplanning and specialist technical work together from the initial site or asset review through consent and implementation.
Planning questions
What determines the planning programme?
The route, site constraints, design work, specialist evidence, engagement and authority process all affect the programme. Agree the information needed and dependencies early, including the work that will remain after a decision.
Planning questions
What if the scheme has stalled or permission has been refused?
Establish what has stopped progress: the planning case, design, missing evidence, contradictory advice or the decision itself. Review the relevant record and the client’s objective before selecting the next route.
Planning questions
When should we address conditions and consent deadlines?
Review conditions before the decision where possible, then build a discharge programme promptly after consent. Each requirement may have a different trigger, including commencement, occupation or an ongoing operation.
Planning questions
Can we start before pre-commencement conditions are resolved?
Starting without satisfying a relevant pre-commencement condition can put lawful implementation at risk and lead to enforcement. The precise wording and circumstances matter.
Planning questions
What does implementing a consent involve?
Establish whether the approved development has lawfully begun, with the relevant requirements addressed. Condition discharge, works on site and the evidence of commencement need to be considered together.
Planning questions
Can conditions or the approved scheme be changed?
In England, the appropriate route depends on the proposed change. A section 73 application may vary or remove conditions within its scope; a non-material amendment or a fresh application may be appropriate in other circumstances.
Planning questions
Can an expiring or lapsed permission be extended or recovered?
Do not assume that the deadline can be extended. In England, section 73 cannot extend the time to begin development or submit reserved matters. Review the consent and implementation evidence before it expires.
Planning questions
What happens to conditions if the site is sold?
Planning permission normally benefits the land, rather than just the original applicant. A sale does not by itself remove its conditions; exceptions must be checked.
Planning questions
How does Community Infrastructure Levy affect commencement?
Where CIL applies, commencement is a critical trigger. Check liability, relief or exemption requirements, notices and the authority’s payment arrangements before starting. Payment may follow an instalment policy rather than all falling due immediately.
Planning questions
What if work has begun without permission or contrary to conditions?
Review the works, planning history and any notice promptly. In England, a retrospective application may be an option, but approval is not assured; an enforcement notice can affect the available application and appeal routes.